As a result of competitor's actions, a project was pushed to completion without all of the envisioned features. This project termination is termed ?

As a result of competitor's actions, a project was pushed to completion without all of the envisioned features. This project termination is termed __________ ?


a) Normal
b) Premature
c) Perpetual
d) Failed
e) Changed Priority