The third step in the Change Management Plan is to _____, where milestones are identified and monitored using various tools such as the Gantt Chart and PERT Chart.

The third step in the Change Management Plan is to _____, where milestones are identified and monitored using various tools such as the Gantt Chart and PERT Chart.


a) assess willingness, readiness, and ability to change
b) develop of adopt a strategy for change
c) implement the change management plan and track progress
d) evaluate experiences and develop lessons learned
e) define, develop and deploy the infrastructure