With the _____, the project team can learn from its experiences during the initial implementation so that later implementations run more smoothly.
a) Direct Cutover
b) Parallel
c) Phased
d) All of the above
e) None of the above
a) Direct Cutover
b) Parallel
c) Phased
d) All of the above