When a joint contract is not carried out may the aggrieved party must sue ( ).

When a joint contract is not carried out may the aggrieved party must sue ( ).


a. Either of joint- parties individually
b. All of joint-parties together
c. None of joint-parties
d. Several-parties

Answer: b