A firm practices the pure chase strategy. Production last quarter was 1000. Demand over the next four quarters is estimated to be 900, 700, 1000, and 1000. Hiring cost is $20 per unit, and firing cost is $5 per unit. Over the next year, the sum of hiring and firing costs will be

A firm practices the pure chase strategy. Production last quarter was 1000. Demand over the next four quarters is estimated to be 900, 700, 1000, and 1000. Hiring cost is $20 per unit, and firing cost is $5 per unit. Over the next year, the sum of hiring and firing costs will be




a. $500
b. $2,500
c. $7,500
d. $7,000
e. $12,500



Answer: C