Which of the following best describes a gross material requirements plan?

Which of the following best describes a gross material requirements plan?




a. a schedule that shows total demand for an item, and when it must be ordered from a supplier or when production must be started
b. an intermediate range plan for the scheduling of families of products
c. a chart illustrating whether capacity has been exceeded
d. a table that corrects scheduled quantities for inventory on hand
e. a schedule showing which products are to be manufactured and in what quantities



Answer: A