In connection with a standard cost system being developed by Flint Co., the following information is being considered with regard to standard hours allowed for output of one unit of product: Average historical performance for the past three years: 1.85 Production level to satisfy average customer demand over a seasonal time span: 1.60 Engineering estimates based on attainable performance: 1.50 Engineering estimates based on ideal performance: 1.25 To measure controllable production inefficiencies, what is the BEST basis for Flint to use in establishing standard hours allowed?

In connection with a standard cost system being developed by Flint Co., the following information is being considered with regard to standard hours allowed for output of one unit of product:
Average historical performance for the past three years: 1.85
Production level to satisfy average customer demand over a seasonal time span: 1.60
Engineering estimates based on attainable performance: 1.50
Engineering estimates based on ideal performance: 1.25
To measure controllable production inefficiencies, what is the BEST basis for Flint to use in establishing standard hours allowed?






a. 1.25
b. 1.50
c. 1.60
d. 1.85




Answer: B