After a contractor declares that he is substantially complete on a project, the owner and/or CM should prepare what document?

After a contractor declares that he is substantially complete on a project, the owner and/or CM should prepare what document?



A) Bond release
B) Punchlist
C) Commissioning plan
D) Final payment





Answer: B