Construction management had its beginnings in the early to mid-1960's. Which of the following factors contributed to the initial use of this delivery system?

Construction management had its beginnings in the early to mid-1960's. Which of the following factors contributed to the initial use of this delivery system?




A) The need to reduce the overall time and cost associated with project delivery.
B) The increasing cost of money and the unpredictability of project funding streams.
C) The changing role of the general contractor and the increasing numbers of specialty trade contractors.
D) All of the above.




Answer: D