Under a CM-at-risk contract, which of the following statements are true?

Under a CM-at-risk contract, which of the following statements are true?




A) The CM, in most cases, holds the trade and/or specialty contracts.
B) The CM has the right to enforce the schedule, pay the trade or subcontractors, and terminate them if such action becomes necessary.
C) On some CM-at-Risk contracts, the CM has the option of performing portions of the work with its own resources (unless prohibited by law on certain public projects).
D) All of the above






Answer: D