Assume that the total complexity factor (TCF) for the software project is 1.1, the Unadjusted Function Point (UFP) for the project is 153 and the productivity figure is 20 function points per person-month. What is the function point (FP) for the project, and what is the estimated effort in person-months for this project?

Assume that the total complexity factor (TCF) for the software project is 1.1, the Unadjusted Function Point (UFP) for the project is 153 and the productivity figure is 20 function points per person-month. What is the function point (FP) for the project, and what is the estimated effort in person-months for this project?


Answer: FP = 153 x 1.1 = 168.3 ;  
Estimated Effort =  168.3 / 20 = 8.4 person-months