Consider the COCOMO project effort estimation methodology. What are the 8 project characteristics that you need to consider in order to decide the project mode?

Consider the COCOMO project effort estimation methodology.


What are the 8 project characteristics that you need to consider in order to decide the project mode?


Answer:
      1. The team’s understanding of the project objectives.
      2. The team’s experience with similar or related projects.
      3. The project’s need to conform with established requirements.
      4. The project’s need to conform with established external interfaces.
      5. The need to develop the project concurrently with new systems and new operational procedures.
      6. The project’s need for new and innovative technology, architecture, or other constraints.
      7. The project’s need to meet or beat the schedule.
      8. The project’s size range.